11-430-130 Kicker Failed to Complete Cycle RAP

11-430-130 The kicker failed to complete a cycle, either to extend or retract.
Initial Actions
Check the following:
If the kicker fingers are jammed against the left side of bin 1 or bin 2, perform the follow-
ing:
For Bin 1:
1.
Enter dC330, code 11-031 bin 1 elevator motor up. Fully raise bin 1.
2.
Remove the bin 1 thumbscrew, PL 11.52 Item 12.
3.
Pull the bin 1 tray assembly, PL 11.52 Item 10 away from the machine until the kicker
fingers are released.
4.
Re-install the bin 1 tray assembly then the thumbscrew.
5.
Enter code 11-032 bin 1 elevator motor down. Lower bin 1 approximately 100mm (4
inches).
For Bin 2:
1.
Enter dC330, code 11-037 bin 2 elevator motor up. Fully raise bin 2.
2.
Remove the bin 2 thumbscrew, PL 11.54 Item 15.
3.
Pull the bin 2 tray assembly, PL 11.54 Item 10 away from the machine until the kicker
fingers are released.
4.
Re-install the bin 2 tray assembly then the thumbscrew.
5.
Enter code 11-038 bin 2 elevator motor down. Lower bin 2 approximately 100mm (4
inches).
The kicker fingers, PL 11.49 Item 19, for damage, paper debris or other obstructions that
would prevent operation.
The kicker frame, PL 11.49 Item 14, for damage or other obstructions that would prevent
operation.
If there is a high level of static on the sheets or the stack. Check that the following static
eliminators are grounded and in good condition:
Static eliminator, PL 11.32 Item 5.
Static eliminator (part of eject housing), PL 11.47 Item 10.
If the output sheets are curled, go to IQ5 Print Damage RAP.
If the output stacking is poor, go to the 11G-130 HCSS Poor Stacking RAP.
Kicker failures can be caused by large sheets being stacked over small sheets, Advise
the customer to clear the bins before following a small sheet job with a large sheet job.
Procedure
Enter dC330, code 11-313. Figure 1, pull down, then release the kicker fingers to actuate the
compiler carriage 90% full sensor, Q11-313. The display changes.
Y
N
Go to Flag 1. Check the sensor.
Refer to:
GP 11 How to Check a Sensor.
P/J407, Carriage PWB.
11C-130 HCSS Power Distribution RAP.
A
Status Indicator RAPs
11-430-130
A
Install new components as necessary:
Carriage PWB, PL 11.46 Item 5.
Compiler carriage 90% full sensor, PL 11.49 Item 5.
Enter dC330, code 11-314. Figure 1, pull down, then release the kicker fingers, to actuate the
compiler carriage bin height sensor, Q11-314. The display changes.
Y
N
Go to Flag 2. Check the sensor.
Refer to:
GP 11 How to Check a Sensor.
P/J407, Carriage PWB.
11C-130 HCSS Power Distribution RAP.
Install new components as necessary:
Carriage PWB, PL 11.46 Item 5.
Compiler carriage bin height sensor, PL 11.49 Item 5.
Enter dC330, code 11-430, to energise the kicker solenoid SOL 11-430, Figure 1. The
noid energises.
Y
N
Go to Flag 3. Check the solenoid.
Refer to:
GP 12 How to Check a Solenoid or Clutch.
P/J402, Carriage PWB.
11C-130 HCSS Power Distribution RAP.
Install new components as necessary:
Carriage PWB, PL 11.46 Item 5.
Kicker solenoid, PL 11.49 Item 4.
Go to the 11-120-130, 11-122-130 Compiler Carriage Jam RAP, and check the compiler sensor
Q11-120.
If the fault still occurs or is intermittent, install a new kicker assembly, PL 11.49 Item 15.
August 2007
2-432
sole-
WorkCentre 5687 Family

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Wc5632fWc5545fWc5675fWc5645fWc5687fWc5655f

Table of Contents