10-101B, 10-102B, 10-103B Lead Edge Late to Fuser Exit
Switch RAP (65- 87 ppm)
10-101 The lead edge of the paper failed to actuate the fuser exit switch within the correct time
after the registration clutch was energized for a simplex sheet.
10-102 The lead edge of the paper failed to actuate the fuser exit switch within the correct time
after the registration clutch was energized for a duplex sheet side 1.
10-103 The lead edge of the paper failed to actuate the fuser exit switch within the correct time
after the registration clutch was energized for a duplex sheet side 2.
WARNING
Do not touch the fuser while it is hot.
Initial Actions
•
Make sure that the correct RAP is used. To identify the correct RAP to use, go to 10-101,
10-102, 10-103 Lead Edge Late to Fuser Exit Switch Entry RAP.
•
Check the condition of the paper in all trays. Refer to IQ1 and GP 20.
•
Check for obstructions in the registration transport, Figure 2.
•
Check for obstructions in the short paper path assembly, Figure 3.
•
Check that the short paper path assembly latches without excessive force, PL 10.25 Item
1. Go to REP 10.1. In Replacement Step 5, check the latch mechanism.
•
Check the stripper fingers on the xerographic module.
•
Check for paper in the fuser module.
•
Check the fuser stripper fingers for contamination, (65-87 ppm) PL 10.10 Item 4.
•
If a 10-101 is caused by paper fed from the bypass tray, check for paper skew.
•
If a 10-103 is caused by a skewed sheet on side 2, check the inverter PL 10.11 Item 23.
Also check the duplex paper path (65-87 ppm) PL 8.20 Item 1. Install new components as
necessary.
•
If 10-101 jams, check that all of the HT connectors are pushed fully home on the HVPS.
Procedure
NOTE: The door interlock switch must be cheated when checking +24V components.
Enter dC330 code 10-100 fuser exit switch, S10-100. Press Start. Manually actuate the switch
with a piece of paper, Figure 1. The display changes.
Y
N
Go to Flag 1. Check S10-100. Refer to:
•
GP 13 How to Check a Switch.
•
Figure 1.
•
P/J35, IOT PWB.
•
01D +3.3V Distribution RAP.
•
01B 0V Distribution RAP.
Install new components as necessary:
•
Fuser exit switch, (65-87 ppm) PL 10.10 Item 11
A
WorkCentre 5687 Family
A
•
Perform OF7 IOT PWB Diagnostics RAP before a new IOT PWB is installed, PL
1.10 Item 2.
Enter dC330 code 10-065 vacuum transport fan, MOT10-065. Figure 3. Press Start, The
runs.
Y
N
Go to Flag 2. Check MOT10-065. Refer to:
•
GP 10 How to Check a Motor.
•
Figure 3.
•
P/J5, IOT PWB.
•
P/J17, LVPS.
•
Fuse, PL 1.10 Item 9, GP 7.
•
01G +24V Distribution RAP.
•
01B 0V Distribution RAP.
Install new components as necessary:
•
Short paper path assembly, PL 10.25 Item 1.
•
Perform OF7 IOT PWB Diagnostics RAP before a new IOT PWB is installed, PL
1.10 Item 2.
Enter dC330 code 04-010 main drive motor. Press Start. Add code 08-070 registration clutch,
CL08-070. Press Start.
NOTE: The clutch will switch off after 5 seconds.
The jam clearance knob 4c, PL 8.17 Item 10, rotates.
Y
N
Go to Flag 3. Check CL08-070. Refer to:
•
GP 12 How to Check a Solenoid or Clutch.
•
P/J5, IOT PWB.
•
P/J17, LVPS.
•
Fuse, PL 1.10 Item 9, GP 7.
•
01G +24V Distribution RAP.
•
01B 0V Distribution RAP.
Install new components as necessary:
•
Registration clutch, (65-87 ppm) PL 8.17 Item 7.
•
Perform OF7 IOT PWB Diagnostics RAP before a new IOT PWB is installed, PL
1.10 Item 2.
Enter dC330 code 08-150 registration sensor, Q08-150. Press Start. Manually actuate the sen-
sor with a piece of paper, Figure 2. The display changes.
Y
N
Go to Flag 4. Check Q08-150. Refer to:
•
GP 11 How to Check a Sensor.
•
Figure 2.
•
P/J16, IOT PWB.
•
01E +5V Distribution RAP.
•
01B 0V Distribution RAP.
B
August 2007
2-257
fan
Status Indicator RAPs
10-101B, 10-102B, 10-103B