ASSEMBLY

Preparation
m WARNING
Danger of severe burns and scalds!
Wear heat resistant gloves!
• Heat the gearbox housing with hot air (or in an
oven) to approx. 100 to 120 °C (212 to 248 F°).

INSTALLATION OF THE BALL BEARING

Step
Procedure
1
Press the oil seal AS 48x72x8 into the
gearbox housing (from inside) using in-
sertion jig part no. 877650 and press-in
mushroom part no. 276964.
NOTE
Lubricate sealing lips with engine oil.
Figure 6.43
Insertion jig 877650
1
3
Oil seal
72–10–00
Page 32
August 01 2018
BRP-Rotax
MAINTENANCE MANUAL HEAVY
Press-in mushroom
2
276964
Step
Procedure
2
Insert the ball bearing (balls must be visi-
ble - cage facing the propeller side) into
the gearbox housing using insertion jig.
part no. 877650 and press-in mushroom
part no. 276966.
Figure 6.44
Insertion jig 877650
1
Ball bearing
3
Step
Procedure
3
Install the retaining ring with circlip pliers.
NOTE
Place the circlip in the groove with the sharp
edge pointing away from bearing.
Press-in mushroom
2
276966
Effectivity: 915 i A Series