Driving modes
6.5 Installing/removing outrigger beams
6 - 62
•
Lift the outrigger beam as far as possible
into the supporting box.
Correct the height so that it does not remain
hanging on the edges (1).
•
Remove the lifting gear from the centre of
gravity.
•
Fasten the lifting gear (1) and a chain hoist.
•
Fasten the chain hoist with a suitable
mounting device on the bore hole (2).
•
Pull the outrigger beam in so far until the
connecting points (1) align.
•
Remove the chain hoist and lifting gear.
3 112 xxx en
Operating Manual GMK6300L