Rigging for crane
operation
Operating Manual GMK6300L
•
Slacken the hoist rope and derrick the main
boom simultaneously.
•
Raise the main boom until the boom head
is in a vertical position above the block
hook (1).
•
Detach the block hook from the retaining
ropes (2).
•
(A) – Pull the pin (3) out.
•
(B) – Raise the hook block (1) above the
hook (2 until the connecting points are
aligned.
•
Insert the pins (3) and secure them with the
retaining pins.
3 112 xxx en
Rigging work
12.8 Rigging work on the main boom
12 - 91
Need help?
Do you have a question about the Grove GMK6300L and is the answer not in the manual?
Questions and answers