Driving modes
6.5 Installing/removing outrigger beams
6.5.2
H
6 - 50

CHECKLIST: Installing the outrigger beams

This checklist is not a complete operating manual. There are accompanying
instructions, which are indicated by cross-references.
Observe the warnings and safety instructions there!
1. Prepare the truck crane for the installation of the outrigger beams;
à
p. 6 - 52.
2. – Remove the connection elements from the supporting box.
– Sling the outrigger beams at their centre of gravity.
– Lift the outrigger beams into the outrigger boxes and remove the
lifting gear.
à
Inserting the outrigger beam , p. 6 - 61
3. Sling the outrigger beams and pull into the outrigger boxes until the
connection points align;
4. Establish the connection to the support box;
5. – Establishing hydraulic connections;
– Establish the electrical connection if necessary;
à
p. 6 - 61.
3 112 xxx en
à
p. 6 - 59.
à
p. 6 - 55.
à
p. 6 - 56.
Operating Manual GMK6300L

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Grove GMK6300L and is the answer not in the manual?

Questions and answers

This manual is also suitable for:

Grove gmk6300l-1

Table of Contents

Save PDF