6.7.2
Prerequisites
Operating Manual GMK6300L
CHECKLIST: Auxiliary hoist, removing
– The truck crane is supported with the required outrigger span as specified
in the Lifting capacity table ;
– The hoist rope on the auxiliary hoist must be unreeved and wound up.
– The superstructure is slewed to the rear.
– The 54.5 t counterweight combination is resting on the counterweight
à
platform;
p. 12 - 62,
or
– Install the rigging frame for counterweight combinations of up to a maxi-
mum of 26 t (57,320 lbs).
1. – Secure the hoist rope;
2. Connect the hand-held control at the right rear of the turntable;
à
Connecting/disconnecting the hand-held control , p. 12 - 21.
3. Removing the connection to the turntable:
– Lower the lifting frame;
– Remove the connection to the turntable;
– Lower the auxiliary hoist;
4. If necessary, disconnect and stow the hand-held control;
à
Connecting/disconnecting the hand-held control , p. 12 - 21.
à
p. 12 - 30.
à
p. 6 - 101.
à
p. 6 - 100.
à
p. 6 - 100.
3 112 xxx en
Driving modes
6.7 Rigging the auxiliary hoist
à
p. 6 - 98.
s
6 - 91