Schedule Definition 16-11
Schedule Definition—Attached Change Orders
The Schedule Definition—Attached Change Orders feature attaches change
orders to the schedule. This indicates that the change orders are to run at the
times specified on the schedule. A maximum of 100 change orders can be
attached to a single schedule. It is recommended, however, that no more
than 20 be attached.
It is also important to bear in mind the time required to process each change
order before attaching it to an order. No other network configuration
control commands (scheduled and ad hoc) can be executed while a series of
scheduled change orders are processed. Consequently, these other
commands become backlogged waiting for the scheduled change order to
finish.

Accessing this feature

This feature can be accessed by pressing [Commands] on the main
Schedule Definition screen or the Schedule Definition–Attached Reports
screen. After the Commands pop-up window appears, select "Attach
change orders to this schedule".