Installation Procedure
1. Place the Entrance Idler Panel in position.
1. Insert the Shaft through the holes (2) at the left side of the Entrance
Idler Panel.
2. Install the E-Rings (2) at the top and bottom of the Shaft.
3. Connect the Connectors for Solenoids SOL3 & SOL4 to the header.
4. Connect the Connectors for Sensors S2, S3, & S4.
5. Place the sensor cables into the Cable Clamps, and close the
Clamps.
6. Install the screw for the ground strap.
7. Do ADJ 1.7 Idler Panel Magnetic Latches Adjustment.
8. Do ARP 1.15 to install the Docking Bracket.
9. Do GP 6.4 Dock the Punch to connect the Punch to the upstream
and downstream devices.
10. Close the Front Door.
11. Connect the Power Cord.
Adjustments/Repairs
GBC StreamPunch Ultra/Ultra MP
02-03-2017
4-24