INSTALLATION
V-BELT PULLEY - INSTALLATION
Step
1
Push the v-belt pulley completely over the
propeller flange and insert the 9.5x675 v-
belt loosely into the v-belt pulley.
Fig. 6
1. V-belt pulley
3. Propeller flange
NOTICE
WARNUNG
The two pulley carriers must sit with the centring
exactly on the inner side of the propeller flange.
Step
2
Insert both pulley carriers with the cen-
tring towards the inner side of the propel-
ler flange.
3
Push the v-belt pulley onto the two pulley
carriers and tighten with 8 M5x16 Allen
screws and lock washers.
Tightening torque 6 Nm (53.09 in. lb.)
Effectivity: 912 i Series
Edition 1/Rev. 0
BRP-Powertrain
MAINTENANCE MANUAL
Procedure
2. V-belt
Procedure
Fig. 7
1. M5x16 Allen screws
3. Pulley carrier
ALTERNATOR - INSTALLATION
Step
1
Fix the alternator support finger-tight by
means of 2 M6x50 Allen screws and lock
washers.
Fig. 8
1. Generator support
3. M6x50 Allen screws
Step
2
Attach the alternator bracket finger-tight
to the gearbox housing using the two
M8x20 Allen screws and VHZ8 lock wash-
ers.
2. Lock washers
4. V-belt pulley
Procedure
2. M8x20 Allen screw
Procedure
24-30-00
Page 7