Step
7
Connect the connector with the EGT con-
nector.
NOTE:
Compress the connector with
the EGT connector so that the
spring clip latches in.
Fig. 59
1. EGT connector
Step
8
Attach the ignition coil connector to the
double ignition coils and press the EGT
connector into the plug holder.
NOTE:
Check for secure connection.
Fig. 60
1. Ignition coil connector
3. EGT connector
Effectivity: 912 i Series
Edition 1/Rev. 0
BRP-Powertrain
MAINTENANCE MANUAL
Procedure
2. Connector
Procedure
2. Double ignition coils
Step
9
Secure the 12/M6 cable clamp with an
M6x14 Allen screw and washer with
LOCTITE 243.
Tightening torque 10 Nm (88.48 in. lb.).
Fig. 61
1. M5x16 Allen screw
3. 12/M6 cable clamp
NOTICE
WARNUNG
Continuous thread, the Allen screws go into the
intake duct. The Allen screws are therefore
secured with LOCTITE 243.
Leaking Allen screws can cause an excessively
lean mixture!
INSTALLATION OF LEFT-HAND (2/4) AND
RIGHT-HAND (1/3) FUEL RAILS
The fuel rails (2/4) and (1/3) are installed and
removed in the same way. The following should
be noted.
Step
1
Lubricate the O-rings of the injection
valves lightly with KLUEBER ISOFLEX
TOPAS Nb5051.
NOTE:
When a used injection jet is re-
installed, new O-rings must be
installed, and the injection jet
must be inserted by hand.
Procedure
2. 5.3 washer
Procedure