Step
5
Plug in the wiring harness connector ap-
propriately. See also section 76-50-00
Wiring harness.
6
Fix the plug holder with cable ties.
7
Fix the ignition cable with cable ties.
Fig. 77
Fig. 78
1. Plug holder
3. 203x7.6mm cable ties
Effectivity: 912 i Series
Edition 1/Rev. 0
BRP-Powertrain
MAINTENANCE MANUAL
Procedure
2. 94x2.5mm cable ties
4. 142x3.2mm cable ties
FUEL LINE ASSY. - INSTALLATION
The fuel line is installed and removed in the
same way. The following should be noted.
NOTICE
WARNUNG
Install the fuel line assy. in a tension-free
manner. If the line is too far away from the fuel
rail, the fuel line must be adjusted. The sealing
surfaces must be parallel.
Step
1
Fix the fuel line assy. on the left and right
of the fuel rails with banjo bolts.
Tightening torque 25 Nm (18 ft. lb.).
Fig. 79
1. M12x1.5 banjo bolt
3. Fuel hose assy.
Step
2
Secure the 8/M6 cable clamp with an
M6x16 Allen screw and 6.4 washer to the
propeller gearbox with LOCTITE 243.
Tightening torque 10 Nm (88.48 in. lb.).
Procedure
2. A12x18 gasket ring
Procedure
73-10-00
Page 34
July 01/2012

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

912 is912 isc

Table of Contents