Step
3
For pressure sensor and temperature
sensor installation, see section 76-70-00.
Fig. 53
1. Airbox
3. Pressure sensors
Effectivity: 912 i Series
Edition 1/Rev. 0
BRP-Powertrain
MAINTENANCE MANUAL
Procedure
2. Temperature sensor
INSTALLATION
INTAKE MANIFOLD - INSTALLATION
Step
1
Place the insulating flange on the cylinder
heads.
2
Place on the left-hand 2/4 and right-hand
1/3 intake manifolds.
Fig. 54
1. Insulating flange
NOTICE
WARNUNG
1-ear clamps may only be used once!
Step
3
Fix the 2/4, 1/3 intake manifolds with 8
M6x20 hex./torx collar screws from the in-
side outwards.
Tightening torque 10 Nm (88.48 in. lb.).
4
Install new 1-ear clamps.
Procedure