When you are on site for a migration from a DEFINITY system, complete the following
additional tasks before starting the migration:
Task
The customer supplies an
EIA 310D (or equivalent)
standard, 19-inch
(48-centimeter), equipment
rack.
Verify that this rack is
installed correctly.
Verify that cables for the
TN2312BP Internet Protocol
Server Interface (IPSI)
circuit packs are labeled
and that appropriate
connectivity is provided.
Verify that you have the
license file from RFA and
that the file includes the
licensed features.
Verify that you have the
Avaya authentication file
from RFA.
Verify that you have the
required tools on site.
Description
Ensure that you have the screws that come with the
rack for installing in square holes or with adapters.
Ensure that the rail kit for the Avaya-supplied UPS is
installed on the rack or available for installation. For
more information on how to install the rail, see the
documentation that comes with the rail kit.
The TN2312BP Internet Protocol Server Interface
(IPSI) circuit packs runs from the control hardware
rack to the port networks.
For instructions on how to transfer translations using
the Magneto Optical Server Tool, see
translations
on page 766.
Prerequisites
Transferring
Issue 2.1 June 2006
753