When you are on site for a migration from a DEFINITY system, complete the following
additional tasks before you start the migration:
Task
The customer supplies an
open EIA 310D (or
equivalent) standard,
4-post, 19-inch
(48-centimeter), equipment
rack. Verify that this rack is
installed correctly and
solidly secured.
Verify that the cables for the
TN2312BP Internet Protocol
Server Interface (IPSI)
circuit packs are labeled
and that appropriate
connectivity is provided.
Verify that you have the
license file from RFA and
that the files include the
licensed features.
Verify that you have the
Avaya authentication file
from RFA.
Verify that you have the
required tools on site.
Description
Ensure that you have the screws that come with the
rack (for installing in square holes or with adapters).
Ensure that the rail kit for the Avaya-supplied UPS is
installed on the rack or available for installation. For
more information on how to install the rail, see the rail
kit documentation.
The cables for the TN2312BP Internet Protocol Server
Interface (IPSI) circuit packs run from the control
hardware rack to the port networks.
For the Magneto Optical Server Tool, see
translations
on page 683.