5-152 Emergency power conservation recovery procedures
Emergency power conservation
Emergency shutdown of one MS plane
4
5
6
7
8
297-8021-545 Standard 14.02 May 2001
Clear the faults on a minimum of one MS before you continue this procedure.
Clear the correct MS alarms to clear the faults on a minimum of one MS.
Proceed to step 2 when a minimum of one MS is fault free.
To switch clock mastership, type
>SWMAST
and press the Enter key.
Example of a MAP response:
Request to Switch Clock Mastership MS: 0 submitted.
Request to Switch Clock Mastership MS: 0 passed.
If the SWMAST command
passed
failed
Do not continue this procedure until you clear the faults that can prevent the
switch of mastership. To clear the faults preventing the switch of mastership,
clear the correct MS alarms. When you clear the faults, go to step 2.
Wait 10 min to make sure the MS has stability. Verify MS and continue this
procedure.
To manually busy the slave MS, type
>BSY
ms_number
and press the Enter key.
where
ms_number
is the number of the slave MS (0 or 1)
Example of a MAP response:
Request to MAN BUSY MS: 0 submitted.
Request to MAN BUSY MS: 0 passed.
(continued)
Do
step 7
step 6