Emergency shutdown of one enhanced network plane
and press the Enter key.
where
Example of a MAP display
Request to QUERY DELOAD ENET
Request to QUERY DELOAD ENET
Plane:0 Shelf:00
5
Proceed to the next step when you confirm that you deloaded all crosspoint
cards on the plane shelf.
6
To access the System level of the MAP display, type
>SYSTEM
and press the Enter key
Example of a MAP display
SYSTEM
Shelf
7
Select a shelf to remove from service.
8
To identify the message switch (MS) card chain connected to the shelf you
selected, type
>TRNSL
and press the Enter key.
where
Example of a MAP display
Request to TRNSL ENET Plane:0 Shelf:00 submitted.
Request to TRNSL ENET Plane:0 Shelf:00 passed.
ENET Plane:0 Shelf:00 MS:0 and 1 Card:20 Link:00 Port:00
9
Note the card number and link number.
10
To manually busy the plane shelf, type
>BSY
Emergency power conservation recovery procedures
plane_no
is the network plane number (0 or 1)
901234567890123456789012
–––––––––––YYYYYYYYY––YY
Note: A Y under the slot number indicates a deloaded crosspoint card in
the MAP display.
Plane 0
00
.
plane_no
shelf_no
plane_no
is the network plane number (0 or 1)
shelf_no
is the network shelf number (0 to 7)
plane_no
shelf_no
DMS-100 Family NA100 Recovery Procedures LET0015 and up
Emergency power conservation
Plane:0 submitted
Plane:0 passed
11111111112222222222333
Plane 1
5-115