Recovering from a dead system in a SuperNode SE switch
188
Determine the system recovery status.
If
any Series III PMs in an LPP or
ELPP failed recovery
any Series III PMs in the SCC
failed recovery
any Series I or II PMs failed re-
covery
any IODs or other devices and
services failed recovery
the system recovered completely step 194
189
Perform the procedure Recovering link peripheral processors in this
document to manually recover the PMs.
Complete the procedure and return to this point.
Go to step 187.
190
Perform the procedure Recovering SuperNode SE application specific units
in this document to manually recover the PMs.
Complete the procedure and return to this point.
Go to step 187.
191
Perform the correct procedures in Alarm and Performance Monitoring
Procedures to manually recover the PMs in the required order.
Complete the procedure and return to this point.
Go to step 187.
192
Manually recover IODs and other devices and services. Perform the correct
procedure in this document. Consult your site operation procedures.
193
For additional help, contact the next level of support.
194
The procedure is complete.
System level recovery procedures
DMS-100 Family NA100 Recovery Procedures LET0015 and up
Do
step 189
step 190
step 191
step 192
2-119
(end)