CHARGING SYSTEM
Install the brush holder [1] as shown and tighten the two
screws (4 x 6 mm) [2].
Install the brush holder insulator [3].
• Take care not to damage the rotor shaft slip rings
with the brush holder during installation.
Install the rear end cover [4].
Install the terminal plate [1] and tighten the three nuts
[2] and screw (5 x 8 mm) [3].
Install the insulator bushing [4] and tighten the nut [5] to
the specified torque.
TORQUE: 7.8 N·m (0.80 kgf·m, 5.8 lbf·ft)
Install the alternator pulley [1] and tighten the alternator
rotor shaft [2] by holding the pulley lock nut [3].
TORQUE: 110 N·m (11.2 kgf·m, 81 lbf·ft)
Install the alternator (page 7-5).