General Information
Installation Checklist
Complete and return the Installation Checklist (107168-XXXX) for Fortus 360mc/400mc
systems when the Setup and Installation is accomplished.
Installation
Un-Crate the System
Refer to the Site Preparation Guide for detailed information on site requirements and
uncrating.
Stabilize System
1.
Roll the system into the desired operating position.
The stabilizing pads are not intended to be used as level adjustments
for the platen. They are to be used to stabilize the system after it has
been moved to its operating location.
Stabilizing Pad
2.
Loosen the locknuts on the four stabilizing pads (one in each corner of the system).
3.
Lower each pad until they touch the floor.
4.
Turn each pad an additional 1 turn after it contacts the floor.
5.
Tighten the stabilizing pad locknuts against the bottom of the system frame.
FORTUS 360mc/400mc Service Manual
Figure 3-1: Stabilizing Pads
Locknut
3-2