Z Zero Calibrations
The Z Zero calibrations are used by the machine to reference the location of the build sheet
compared to the model tip in the Z axis. If positioned at Z Zero, the end of the model tip
should be at the top of the build sheet. The Z zero value is critical to ensure the first layer of a
build adheres properly to the build sheet.
Manual Z Zero Calibration
The Manual Z Zero Calibration is used to establish an approximate Z Zero location which
will allow the Auto Z Zero calibration to complete successfully. During the Manual Z Zero
Calibration the operator manually positions the Z Stage at the desired Z Zero position and
captures the position. The Manual Z Zero Calibration is typically performed if an Auto Z
Zero Calibration fails.
Procedure
1.
Install a new build sheet and verify that vacuum is present.
2.
From the Main Menu on the operator control panel select: Operator Control > Calibrate
> Set Z Stage Zero > Set Manual Z Zero. Allow the system to reach position.
3.
Use the operator control panel to position the Z stage so the model tip is at the top of the
build sheet.
Caution: Be sure to use the proper increment when positioning the Z
Stage. Using an improper value can cause damage to the head and
platen.
• Look for the reflection of the model tip in the build sheet. When the
• The tip should be within 0.030 in. (0.762 mm) of the top of the build sheet
Model Tip
Model Tip Reflection
4.
Select Set Z Stage = 0 and press enter.
5.
Run the Auto Z Zero Calibration. (See
FORTUS 360mc/400mc Service Manual
reflection of the tip looks like it is just touching the real tip the position is
correct.
without touching.
Figure 6-1: Manual Z Zero Calibration
"Auto Z Zero Calibration" on page
Build Sheet
6-4).
6-3