M800V/M80V Series PLC Development Manual
5 Peripheral Development Environment (GX Works2)
5.5 Common Items
 How to connect to projects 5 and 6
The figure below shows how to connect to projects 5 and 6.
[Screen for selecting connection target]
Change target CPU to 1 or 2 to switch
the projects to connect to 5 or 6.
Setting items
Network Communication Route
Access to other stations in the same loop or multi-tier system
Network No.
Station No.
Multi CPU setting
CPU 1 and 2
(*1) Double-click [Ethernet] to display the setting item.
Click
[Precaution]
Connection is impossible
without setting Multiple CPU
Setting.
[Precaution]
Only Network No. 2, Station
No. 2 can be connected.
Setting
Ethernet
2
2
Switch to multi-project 5 and 6
79
Remarks
(*1)
IB-1501614-B