Xerox ColorQube 9303 Series Service Manual page 515

Table of Contents

Advertisement

Table 1 PEST Hard and Soft Fault Codes
Code
Hard/Soft
Action
99-430
Hard
Go to the
01A
AC Power Distribution RAP. Select the Head 3 Reser-
voir and Jetstack Heaters Check. Install new components as
required.
99-431
Hard
Go to the
01A
AC Power Distribution RAP. Select the Head 3 Reser-
voir and Jetstack Heaters Check. Install new components as
required.
99-432
Hard
Go to the
01A
AC Power Distribution RAP. Select the Head 4 Reser-
voir and Jetstack Heaters Check. Install new components as
required.
99-433
Hard
Go to the
01A
AC Power Distribution RAP. Select the Head 4 Reser-
voir and Jetstack Heaters Check. Install new components as
required.
99-434
Hard
Go to the
01A
AC Power Distribution RAP. Select the Head 1 Reser-
voir and Jetstack Heaters Check. Install new components as
required.
99-435
Hard
Go to the
01A
AC Power Distribution RAP. Select the Head 1 Reser-
voir and Jetstack Heaters Check. Install new components as
required.
99-436
Hard
Go to the
01A
AC Power Distribution RAP. Select the Head 2 Reser-
voir and Jetstack Heaters Check. Install new components as
required.
99-437
Hard
Go to the
01A
AC Power Distribution RAP. Select the Head 2 Reser-
voir and Jetstack Heaters Check. Install new components as
required.
99-438
Hard
Go to the
01A
AC Power Distribution RAP. Select the Head 3 Reser-
voir and Jetstack Heaters Check. Install new components as
required.
99-439
Hard
Go to the
01A
AC Power Distribution RAP. Select the Head 3 Reser-
voir and Jetstack Heaters Check. Install new components as
required.
99-440
Hard
Go to the
01A
AC Power Distribution RAP. Select the Head 4 Reser-
voir and Jetstack Heaters Check. Install new components as
required.
99-441
Hard
Go to the
01A
AC Power Distribution RAP. Select the Head 4 Reser-
voir and Jetstack Heaters Check. Install new components as
required.
99-442
Soft
Go to the
01A
AC Power Distribution RAP. Select the Head 1 Reser-
voir and Jetstack Heaters Check. Install new components as
required.
99-443
Soft
Go to the
01A
AC Power Distribution RAP. Select the Head 1 Reser-
voir and Jetstack Heaters Check. Install new components as
required.
ColorQube® 9303 Family
99-444-00 to 99-457-00 PEST Error 16 RAP
99-444-00 Heater, jet stack H2 left below min.
99-445-00 Heater, jet stack H2 right below min.
99-446-00 Heater, jet stack H3 left below min.
99-447-00 Heater, jet stack H3 right below min.
99-448-00 Heater, jet stack H4 left below min.
99-449-00 Heater, jet stack H4 right below min.
99-450-00 Heater, jet stack H1 left above max.
99-451-00 Heater, jet stack H1 right above max.
99-452-00 Heater, jet stack H2 left above max.
99-453-00 Heater, jet stack H2 right above max.
99-454-00 Heater, jet stack H3 left above max.
99-455-00 Heater, jet stack H3 right above max.
99-456-00 Heater, jet stack H4 left above max.
99-457-00 Heater, jet stack H4 right above max.
Initial Actions
Ensure that the electricity to the machine is switched off while performing tasks that do
not need electricity. Refer to
death or injury. Moving parts can cause injury.
Procedure
Refer to
Table
1. Perform the relevant action. For an explanation of PEST codes refer to
dC123.
Table 1 PEST Hard and Soft Fault Codes
Code
Hard/Soft Action
99-444
Soft
Go to the
voir and Jetstack Heaters Check. Install new components as required.
99-445
Soft
Go to the
voir and Jetstack Heaters Check. Install new components as required.
99-446
Soft
Go to the
voir and Jetstack Heaters Check. Install new components as required.
February 2013
99-429-00 to 99-443-00, 99-444-00 to 99-457-00
2-491
WARNING
GP
14. Disconnect the power cord. Electricity can cause
01A
AC Power Distribution RAP. Select the Head 2 Reser-
01A
AC Power Distribution RAP. Select the Head 2 Reser-
01A
AC Power Distribution RAP. Select the Head 3 Reser-
Status Indicator RAPs

Advertisement

Table of Contents
loading

Table of Contents