Figure 8-39
Topology
● Re-connect to the target device.
● Load the project into the drive with "Download"
● Persistently save with RAM→ROM.
● The LEDs on the Terminal Module now light up green and the parameters of the
additional DOs can be accessed.
8.6.1.2
Commissioning via parameter assignment
With the electronics power supply switched-off, plug in the Terminal Module with Drive-CLiQ
at X100 or X101.
Accept the additional components by writing the following parameter to the CU
Note
When powering up on a drive for the first time, the software will, if required, be loaded into
the Terminal Module. After successful loading, the LED on the SMC30 flashes red/green and
alarm A1007 is output. A POWER OFF/ON is required before the component can be used.
p0009=1
p9910=1 (= accept components)
p0009=0
The software restarts and accepts the additional components.
If you then go online with an old STARTER project, the different topologies will be displayed
offline and online. With "Load to PG" the changed topology can also be accepted by
STARTER
SINAMICS DCM DC Converter
Operating Instructions, 02.2015, A5E34763375/RS-AA/001
8.6 Commissioning optional additional modules