Avaya MCC1 Installation And Upgrades page 232

Media gateways installation and avaya definity server si upgrades made easy
Hide thumbs Also See for MCC1:
Table of Contents

Advertisement

System 75 XE to R8si (Blowback)
Task List: System 75 XE to R8si
3
Identify and record customer-placed busy-outs.
Execute
placed by the customer.)
NOTE:
You will restore the customer-placed busy-outs after you have upgraded the system.
4
For a system that has existing BX.25 links that are being retained after the upgrade: identify and
record them.
Execute
5
Execute the following commands and verify that the information is correct:
list station
list trunk-group
list hunt-group
list data-module
For upgrades from systems later than G1,
For a system with Expert Agent later than G3V3,
If any command does not complete successfully, escalate the problem immediately.
Return to Task List
Disable scheduled maintenance and alarm origination [75 XE upgrade]
Return to Task List
1
To prevent scheduled daily maintenance from interfering with the update or upgrade, type
change system-parameters maintenance
2
If scheduled maintenance:
— has begun: set the Stop Time field to 1 minute after the current time.
— has not begun: set the Start Time field to at least 8 hours after the upgrade starts.
CAUTION:
If you do not disable Alarm Origination, the system may generate alarms, resulting in
unnecessary trouble tickets.
3
Type neither in the Alarm Origination to OSS Numbers field and press Enter.
Return to Task List
232
(Examine the error log and record the error 18s that identify the busy-outs
display errors
display communication-interface links
list ars analysis
list agent
and press Enter.
SI Installation and Upgrades
June 2004