7-2
Battery Capacity Re-Calibration on V3/V4 Control Stations
1. From behind the Browser, launch a command window (see
page
120).
A command window appears with an ADS prompt.
2. Change to the /export/home/insite/browser directory, by entering:
cd /export/home/insite/browser
3. Connect to the UPS web-based diagnostics, by entering:
mozilla-bin http://localhost:3052
4. At the login page that appears, specify root for the username and root for the password.
5. Note that the calibration process will not start if the battery charge is less than 100%. To display Bat-
tery Capacity , select from the left menu Smart-UPS 750 RM ->Status.
6. Prevent the system from being shut down during the calibration process, do the following:
a. Select the left menu Event, then Actions, and click on the Battery discharged event.
b. Under the Command file item, uncheck the Enable command file execution checkbox.
c.
Under Shutdown, uncheck the Initiate Shutdown Sequence checkbox.
d. Click on the Apply button.
e. Click on the Insufficient Runtime Available event.
f. Under Shutdown uncheck the Initiate Shutdown Sequence checkbox.
g. Click on the Apply button.
7. Start the calibration process. To do this, select in left menu Smart-UPS 750 RM->Select Diagnos-
tic, under item Initiate diagnostic select diagnostic action Runtime calibration, then click the
Apply button.
8. During the test and calibration process, the following events occur:
-
The ON line led (B) is off, and the On Battery led (E) is on.
-
The UPS beeps.
-
The UPS charge indicator decreases.
Check the test status by clicking on left menu Diagnostics under Smart-UPS 750 RM.
Wait until the Initiate Diagnostics staus changes from (Runtime calibration in progress) to (Run-
time calibration currently unavailable).
Note:
Once you launch a test, the Runtime calibration is not available because battery is in the process
of being discharged.
When the Runtime Calibration test is complete the Runtime Calibration date is updated.
9. Shutdown the AWS system as follows:
a. Select menu Shutdown now under Protected System "Shutdown now". You may need to
login again (as username root, password root) if session has expired.
b. Change the Begin OS Shutdown Sequence In value to 1 second.
c. Select the UPS Shutdown type, Manual Restart.
d. Click on the Apply button.
e. Acknowledge the shutdown.
With the AWS system powered off and power applied to the UPS, the battery takes 45-60 minutes to
recharge.
JC-CHK-A-003.fm
Service Information and Procedures Class A 2385072-16-8EN
Launching a Command Line Window on
Page no. 1739
Senographe DS
Job Card CHK A003 - UPS Batteries
Chapter 9

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents