Job Card Pm A428 - Conditioner Coolant Level Check And Top-Up - GE Senographe DS Manual

Hide thumbs Also See for Senographe DS:
Table of Contents

Advertisement

GE Healthcare
Revision 1
Job Card PM A428 - Conditioner Coolant Level Check and
1
SUPPLIES
Coolant kit
2
TOOLS
Standard Tool Box
Purge Tool
3
REQUIRED EFFORT
Personnel: 1 Field Engineer
Time: 5 minutes
4
SAFETY PRECAUTIONS
When filling or topping up the Conditioner, take great care to keep coolant away from the vents, the
ON/OFF switch and the power cord connection. Do not immerse the Conditioner in any liquid.
Dispose of old and surplus coolant with care as described in the section Surplus Coolant Disposal;
refer to the Caution below.
CAUTION
• Before adding coolant to the Conditioner, always switch OFF the Generator and MDR cir-
cuit breakers in the Generator Cabinet. Switch on the MDR breaker only as instructed.
• Always use a funnel when adding coolant to the Conditioner.
• Always wear protective gloves and goggles when working with coolant.
• When working with coolant you should treat it with care; avoid unnecessary contact .
See below for First Aid advice:
First Aid in case of contact with Conditioner coolant:
Immediately flush eyes or skin with plenty of water for at least 15 minutes.
If coolant contacts the eye, call a physician immediately.
If coolant is swallowed, drink one to two glasses of water or milk. Avoid alcohol. Call a physician
immediately.
Remove and wash contaminated clothing before reuse.
5
PREREQUISITES
Remove the Generator Cabinet covers as required for access to the Conditioner. Refer to
A042 - Remove/Reinstall Generator Covers on page
6
PROCEDURE
CAUTION
When performing any of the following procedures, be careful to avoid spillage of coolant,
especially onto or near electrical connections. If any coolant is spilled, it must be cleaned
up immediately.
JC-PM-A-428.fm
Service Information and Procedures Class A 2385072-16-8EN

Job Card PM A428 - Conditioner Coolant Level Check and Top-up

513.
Page no. 1805
Senographe DS
Top-upChapter 11
Job Card PHY
Chapter 11

Hide quick links:

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Senographe DS and is the answer not in the manual?

Questions and answers

Dr.Robert Mahmut
March 26, 2025

G.E.Essential l have recently bought What is the full weight.of the mamo Full weight of the console and other İtem's also measurements of each item with the main machine please All this Shipping Company required

1 comments:
Mr. Anderson
March 26, 2025

The GE Senographe DS mammography machine is shipped in three crates with the following dimensions and weights:

- Crate 1 (Gantry, Generator Cabinet, and ramp):
- Dimensions: 2066 mm (81.34 in) depth × 848 mm (33.39 in) width × 2292 mm (90.24 in) height
- Mass: 641 kg (1410.2 lbs)

- Crate 2 (Control Station):
- Dimensions: 1110 mm (43.70 in) depth × 770 mm (30.31 in) width × 1850 mm (72.83 in) height
- Mass: 210.5 kg (464.07 lbs) for truck transport (without side covers and lid)
- Mass: 223.5 kg (492.73 lbs) for plane/boat transport (with side covers and lid)

- Crate 3 (Detector):
- Dimensions: 872 mm (34.33 in) depth × 2270 mm (89.37 in) width × 260 mm (10.24 in) height
- Mass: 104.4 kg (229.68 lbs)

### Total Mass:
- For truck transport: 641 + 210.5 + 104.4 = 955.9 kg (2104.95 lbs)
- For plane/boat transport: 641 + 223.5 + 104.4 = 968.9 kg (2133.61 lbs)

These values include the gantry, generator cabinet, control station, detector, and all related components.

This answer is automatically generated

Subscribe to Our Youtube Channel

Table of Contents

Save PDF