GE Senographe DS Manual page 1738

Hide thumbs Also See for Senographe DS:
Table of Contents

Advertisement

GE Healthcare
Revision 1
Job Card CHK A003 - UPS Batteries
minutes of run time; you must wait for the battery to recharge before using the system.
2. Start a UPS self test; press and hold the ON/TEST button until a beep is heard and the On Line LED
(B) flashes.
During the test the UPS briefly supplies the load from the battery; the On Battery
the test passes, the On Battery LED goes out and the On Line LED
If the test fails, the UPS returns to on-line status, but the Replace Battery LED
cause should be investigated.
3. To check the input voltage (hospital supply), press and hold the ON/TEST button for at least four sec-
onds (this will start a self test as above):
The Charge/Line Voltage LEDs now indicate the input voltage status; normally two, three, or four
LEDs should light.
If all five LEDs are lit, the input is more than 247 V; if one LED is lit or no LEDs are lit, the input is less
than 213 V.
7
BATTERY CAPACITY RE-CALIBRATION
About once a year, it may be desirable to re-calibrate the battery capacity indicator.
The procedure, including battery recharge, takes about one hour
! Notice:
It may not be possible to start this procedure immediately after the function check described above,
because it requires the battery charge to be 100% of capacity.
7-1
Battery Capacity Re-Calibration on V1/V2 Control Stations
1. From the Service Desktop, click the Diagnostics button
2. To prevent the system from being shut down during the calibration process, select Configuration/
Event Actions, and then the UPS Battery is Discharged event; remove the check mark from the Shut-
down Server box.
3. Note that the calibration process will not start if the battery charge is less than 100%. To display Bat-
tery Capacity (in place of Run Time Remaining), select Configuration/Monitoring Preferences, and
select the parameter to be displayed in the left hand graphical bar of the PowerChute interface.
4. Start the calibration process by selecting Diagnostics/Initiate run Time Calibration.
5. Once started, the calibration process continues until battery capacity falls to 25% (the time from
100% to 25% is about 10 minutes).
With the AWS system powered off and power applied to the UPS, the battery takes 45-60 minutes to
recharge.
6. Before returning the system to normal operation, you must ensure that it will be shut down if battery
capacity is low:
-
EITHER: In the PowerChute interface menu, select Configuration/Event Actions, and select the
UPS Battery is Discharged event; click the Shutdown Server box to restore the check mark.
-
OR: Log in as root in a command window; execute the command ups stop
Chapter 9
Service Information and Procedures Class A 2385072-16-8EN
, then the UPS button.
Page no. 1738
Senographe DS
LED (E) is lit. If
(B) again lights steadily.
(F) is lit. The
JC-CHK-A-003.fm

Hide quick links:

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Senographe DS and is the answer not in the manual?

Questions and answers

Dr.Robert Mahmut
March 26, 2025

G.E.Essential l have recently bought What is the full weight.of the mamo Full weight of the console and other İtem's also measurements of each item with the main machine please All this Shipping Company required

1 comments:
Mr. Anderson
March 26, 2025

The GE Senographe DS mammography machine is shipped in three crates with the following dimensions and weights:

- Crate 1 (Gantry, Generator Cabinet, and ramp):
- Dimensions: 2066 mm (81.34 in) depth × 848 mm (33.39 in) width × 2292 mm (90.24 in) height
- Mass: 641 kg (1410.2 lbs)

- Crate 2 (Control Station):
- Dimensions: 1110 mm (43.70 in) depth × 770 mm (30.31 in) width × 1850 mm (72.83 in) height
- Mass: 210.5 kg (464.07 lbs) for truck transport (without side covers and lid)
- Mass: 223.5 kg (492.73 lbs) for plane/boat transport (with side covers and lid)

- Crate 3 (Detector):
- Dimensions: 872 mm (34.33 in) depth × 2270 mm (89.37 in) width × 260 mm (10.24 in) height
- Mass: 104.4 kg (229.68 lbs)

### Total Mass:
- For truck transport: 641 + 210.5 + 104.4 = 955.9 kg (2104.95 lbs)
- For plane/boat transport: 641 + 223.5 + 104.4 = 968.9 kg (2133.61 lbs)

These values include the gantry, generator cabinet, control station, detector, and all related components.

This answer is automatically generated

Table of Contents

Save PDF