13. Place a septum with a notch cut into it behind the transfer line nut. The septum marks
the place on the column where it should exit the nut.
Figure 18. Positioning the Septum
Column
Measuring Tool
14. Pull the column back from the transfer line nut. Do not move the septum from its
position on the column.
Figure 19. Pulling the Column Back from the Transfer Line Nut
15. Loosen the transfer line nut from the column measuring tool.
16. Remove the column, transfer line nut and ferrule from the column measuring tool,
making sure not to move the septum from its location on the column.
17. Insert the column into the transfer line.