Section 12
Control
666
select
reservation request RES_RQ
reservation granted RES_GRT
command termination
tResResponse
timer
IEC05000093 V1 EN
Figure 333:
tResResponse
The timer tExecutionFB supervises the time between the execute command and the
command termination, see figure 334.
execute command
phase A
open
close
phase B
open
close
open
phase C
close
command termination
phase A
command termination
phase B
command termination
phase C
command termination
circuit breaker open
close
tExecutionFB
timer
* The command termination will be delayed one execution sample.
ANSI05000094 V1 EN
Figure 334:
tExecutionFB
The parameter tSynchrocheck is used to define the maximum allowed time between the
execute command and the input SYNC_OK to become true. If SYNC_OK=true at the
time the execute command signal is received, the timer "tSynchrocheck" will not start.
The start signal for the synchronizing is obtained if the synchronism-check conditions
are not fulfilled.
t1>tResResponse, then
1-of-n-control in 'cause'
t1
en05000093.vsd
*
t1
Technical reference manual
1MRK505222-UUS C
is set
t1>tExecutionFB, then
long-operation-time in
'cause' is set
en05000094_ansi.vsd