2 Installation and commissioning
2.5.1 Lifting robot with fork lift
Continued
12
13
14
80
Action
Carefully lift the robot and move it to its install-
ation site.
WARNING
Personnel must not, under any circumstances,
be present under the suspended load!
Refit the cooling fan to the motor, if any.
© Copyright 2007-2013 ABB. All rights reserved.
Note
Detailed in section
Installation of cool-
ing fan for motors, axes 1-3 (option) on
page
108.
3HAC022033-001 Revision: M