STEP 42
Press the VACUUM key. Automatic will show on the
display. VACUUM will appear on the display and after
a slight delay, the vacuum pump will star t. The
display will show the amount of time programmed
and begin a countdown to zero.
When the programmed time has elapsed, an
automatic hold occurs. Check the low pressure
gauge to see that the A/C system maintains a 28 to
29-1/2 inches of mercury (Hg).
NOTE: The low pressure gauge must not increase
faster than one inch of mercury (Hg) in 15 minutes. If
the system will not hold vacuum, a leak exists that
must be corrected before recharging can begin. See
leak test information in this section.
STEP 43
IMPORTANT: Do not inject the PAG oil until the
system will hold a proper vacuum.
OEM1415 has an injection system to return new SP-
20 PAG oil equal to the amount recovered at the end
of the evacuation process.
To add the new oil, adjust the O-ring around the oil
return bottle to the required oil charge level.
NOTE: If 2.4 oz (71 ml) was recovered in the oil
reservoir, 2.4 oz (71 ml) of new SP-20 PAG must be
returned.
Open the oil injection valve to add the oil into the
system. Close the valve when the oil level reaches
the O-ring.
IMPORTANT: Do not let oil level fall below the dip
tube in the return bottle or air will be introduced into
the refrigerant circuit.
STEP 44
Press the CHARGE key. PROGRAM and CHARGE
will appear on the display.
Section 50 - Climate Control - Chapter 2
50-2-28
2
1
1. OIL RETURN BOTTLE
A22123
MK96C043
2. OIL INJECTION VALVE
A22115