Wall-Mounting a Stand-Alone Processor
Module and a 2-Slot Carrier
Install the processor module within 5 feet (1.5 meters) of a properly grounded wall outlet (not
controlled by a switch) and the network interface jacks.
Follow these steps to wall-mount the module(s):
1. Using the enclosed template, mark the screw
locations on the wall.
2. Hold the processor module against the wall
with the line and extension jacks facing left.
Leave at least 1 foot (0.3 meters) clearance at
the top, front, and right side, and at least 2 feet
(0.6 meter) at the bottom and left side
(see
Figure
). This allows you to access the
jacks or expand the system with another
module, and ensures adequate ventilation.
3. Insert a #8 sheet metal screw into the screw
hole at the top of the processor module
(see
Figure
).
4. If you are installing a second module, go to
Step 5. If you are not installing a second
module (stand-alone configuration):
a. Insert another #8 sheet metal screw into
the screw hole at the bottom of the module.
b. Tighten the screws until the mounting
tracks are snug against the wall. There
must be a 3/8 inch (1 cm) gap between the
wall and the rest of the module. Do not
overtighten the screws or the module will
warp and fail to operate.
c. Go to the next procedure,
on page
2-9.
Figure 2-1. Processor Module
Figure 2-2. Screwing in a Processor
"Labeling Jacks"
2
Clearance
Module
Installing the Control Unit
Installation
2-5