Commissioning
5.1
Commissioning guidelines
Overview
SINAMICS G120X converter
Operating Instructions, 06/2019, FW V1.01, A5E44751209B AC
1. Define the requirements to be
met by the drive for your
application.
(Page 153)
2. Restore the factory settings of
the converter if necessary.
(Page 173)
3. Check if the factory setting of the
converter is sufficient for your
application.
(Page 157)
4. Set the following for quick
commissioning of the drive:
– The closed-loop motor control
– The inputs and outputs
– The fieldbus interface
(Page 159)
5. Check if additional converter
functions are required for the
application.
(Page 153)
6. If necessary, adapt the drive.
(Page 179)
7. Save your settings.
(Page 939)
5
151