Commissioning
5.3 Preparing for commissioning
Procedure for FSH and FSJ
1. Set p0010 = 2.
2. Set the forming duration p3380.
For p3380 > 0, with alarm A07391, the converter signals that at the next ON command, DC
link forming starts.
3. Switch on the motor, e.g. from an inserted operator panel.
4. Wait for the forming time to elapse. r3381 indicates the remaining time.
If the line voltage is switched off before forming has been completed, then you have to form
the DC link again.
5. The converter sets p3380 = 0.
6. Set p0010 = 0.
You have formed the DC link.
Parameter
Parameter
p0010
p3380
r3381
r3382
156
Storage time from the production date
1 ... 2 years
2 ... 3 years
> 3 years
Description
Drive commissioning parameter filter
Forming activation/duration
Remaining forming time
Forming status word
Recommended forming duration
1 hour
2 hours
8 hours
Operating Instructions, 06/2019, FW V1.01, A5E44751209B AC
Factory setting
0
0 h
- h
-