Saving the settings and series commissioning
8.2 Operator panel
8.2
Operator panel
8.2.1

Backup using the operator panel

Precondition
The converter power supply has been switched on.
Function description
Procedure
You have backed up the settings to the BOP-2.
8.2.2

Transfer to the converter

Precondition
The converter power supply has been switched on.
946
1. In the "OPTIONS" menu, select "TO BOP".
2. Start data transfer with OK.
3. Wait until the converter has backed up the settings to the BOP‑2.