NTP-B222 Connect Office Power to the ONS 15327 Shelf (Terminal-Lug Power Connector)
Stop. You have completed this procedure.
Step 10
NTP-B222 Connect Office Power to the ONS 15327 Shelf
(Terminal-Lug Power Connector)
Purpose
Tools/Equipment
Prerequisite Procedures
Required/As Needed
Onsite/Remote
Security Level
This procedure describes the installation of the terminal-lug power connector. To install the screw-lock
Note
power connector also included with the ONS 15327, see the
ONS 15327 Shelf (Screw-Lock Power Connector)" task on page
If you encounter problems with the power supply, refer to the Cisco ONS 15327 Troubleshooting Guide.
Note
Do not apply power to the ONS 15327 until you complete all installation steps and check the continuity
Warning
of the -48 VDC and return.
Cisco ONS 15327 Procedure Guide, R4.0
D-4
This procedure connects power to the ONS 15327 shelf.
#2 Phillips screwdriver
Medium slot head screwdriver
Small slot head screwdriver
Wire wrapper
Wire cutters
Wire strippers
Crimp tool
Fuse panel
Terminal-lug power connectors (2)
Terminal lugs (4)
Terminal lug screws (4)
Power cable (from fuse and alarm panel to assembly), #10 AWG, copper
conductors, 194°F [90°C])
Ground cable #6 AWG stranded
Listed pressure terminal connectors such as ring and fork types; connectors
must be suitable for #10 AWG copper conductors
Labels (2) (one for the A-side power lead and one for the B-side)
DLP-B16 Connect the Office Ground to the ONS 15327, page 1-13
Required
Onsite
None
Appendix D
Alternate Installation Procedures
"DLP-B17 Connect Office Power to the
1-14.