Install Hardware
User-Supplied Materials
These materials and tools are required but are not supplied with the ONS 15327.
Tools Needed
March 2003
Screw-lock power connector
Terminal-lug power connector
Terminal lugs (4)
Terminal lug screws (4)
Straight DS-1 cable
Tie-down bar (optional) (15327-TIE-BAR-19 for a 19-inch rack or 15327-TIE-BAR-23 for a
23-inch rack)
Cable storage tray and screws (4) (optional)
Equipment rack (22 inches total width for a 19-inch rack; 26 inches total width for a 23-inch rack)
Fuse panel
Copper power cable (from fuse and alarm panel to assembly), #12-16 AWG
The National Electrical Code recommends #12-14 AWG power cable
Ground cable, #12 AWG stranded (minimum)
Alarm cable, CAT-5 terminated with RJ-45 for all alarm connections
Building Integrated Timing Supply (BITS) clock cable, #22 or #24 shielded AWG wire
Serial cable, DB-9 connectors
Single-mode SC fiber jumpers with UPC polish (55 dB or better) for OC12 and OC-48 cards and
fiber jumpers with LC connectors for the OC-3 card
Shielded ABAM cable terminated with Champ connectors for DS-1 ports with #22 or #24 AWG
ground wire (optional)
Shielded coaxial cable terminated with BNC connectors for DS-3 ports
Tie wraps and/or lacing cord
Labels
#2 Phillips screw driver
Medium slot head screw driver
Small slot head screw driver
Wire cutters
Wire strippers
Crimp tool
Needle nose pliers (for bail locks on Champ connectors)
Required Tools and Equipment