Note: SDI ports are configured as a pair (for example, 0 and 1 or 2
and 3). Make sure there is no conflict with an existing port.
52 Perform a data dump:
LD 43
EDD
When "DATABASE BACKUP COMPLETE" or "DATADUMP
COMPLETE" displays on the terminal, enter
****
If the data dump is not successful, do not continue; contact your
technical support organization. A data dump problem must be
corrected before proceeding.
53 Verify the system by using the test procedures described in Meridian 1
system installation procedures (553-3001-210) and X11 input/output
guide (553-3001-400). Clear any faults discovered during testing.
54 Follow "Postconversion procedure" in Software conversion procedures
(553-2001-320).
The SL-1 X11 release 21 option 21E is now operational. Install all covers to
complete the upgrade.
Upgrade system installation Upgrading to Meridian 1 system options
Meridian 1 option 21 upgrades
to load the program
to begin the data dump
to exit the program
CAUTION
8-45