15 After the system initializes, reenter system configuration data into the
customer database, if required, in the following sequence:
•
Configure network loops to match loop types and loop numbers of
the current configuration.
•
Configure I/O devices to reflect the current configuration.
•
Reenter customer data blocks. System options and features must
reflect the current configuration.
•
Configure station data blocks.
•
Configure route data blocks.
•
Configure trunk data blocks.
•
Configure remaining system configuration records.
•
Verify system operation before adding new equipment.
•
Configure new equipment and functions, if any.
16 Verify the system by using test procedures described in Meridian 1
system installation procedures (553-3001-210) and X11 input/output
guide (553-3001-400). Clear any faults discovered during testing.
17 Perform the postconversion procedure as outlined in Software
conversion procedures (553-2001-320).
The Meridian 1 X11 release 22 option 51C is now operational. Install all
module covers to complete the upgrade.
Upgrade system installation Upgrading to Meridian 1 system options
SL-1 A, M, S, and MS system upgrades
2-21