22 Perform the appropriate step to restore power in each Core/Network
module.
For AC-powered systems, simultaneously set the circuit breaker on
the MPDU in both Core/Network modules to ON (up position).
For DC-powered systems, simultaneously set the switch on the
module power supply in both Core/Network modules to ON (up
position).
Note: If power to both Core/Network modules is restored
simultaneously, the CMDUs will still be synchronized.
23 After the system initializes, reenter system configuration data into the
customer database, if required, in the following sequence:
Configure network loops to match loop types and loop numbers of
the current configuration.
Configure I/O devices to reflect the current configuration.
Reenter customer data blocks. System options and features must
reflect the current configuration.
Configure station data blocks.
Configure route data blocks.
Configure trunk data blocks.
Configure remaining system configuration records.
Verify system operation before adding new equipment.
Configure new equipment and functions, if any.
24 Verify the system by using test procedures described in Meridian 1
system installation procedures (553-3001-210) and X11 input/output
guide (553-3001-400). Clear any faults discovered during testing.
25 Perform the postconversion procedure as outlined in Software
conversion procedures (553-2001-320).
The Meridian 1 X11 release 21 option 61C is now operational. Install all
module covers to complete the upgrade.
Upgrade system installation Upgrading to Meridian 1 system options
SL-1 L, LE, and N system upgrades
3-23