Upgrading CPU 0

Note 1: Make sure a terminal is connected to J25 on the I/O panel in
Core 0. If you are using only one terminal, connect it to Core 0; if you
are using a switch box for the CPSI ports, set the switch to Core 0. Verify
that the terminal is set for 9600 baud, 7 data bits, 1 stop bit, space parity,
full duplex, XON protocol.
Note 2: If you upgraded the CP and IOP ROMs on Core 1, do the same
for Core 0. Insert diskette 1 from the software upgrade package into
IOP/CMDU 0. Press the MAN RST button on the CP card in Core 0. At
the main menu, select option <e> for the CP ROM, follow the on-screen
directions, and then select option <f> for the IOP ROM. Refer to
"Software Installation Tool reference," Software conversion procedures
(553-2001-320). Do not install software or the customer database on
Core 0.
1
If the Clock Controller Card for the Core Module was previously
installed in the XT/71, move the card from CPU 0 to Core 0:
2
For QPC471 cards only, set SW1, SW2, and SW4 as shown (see
Table 12-35).
3
Set the ENB/DIS switch on the QPC471H to DIS and install the card in
slot 6.
Table 12-35
QPC471H Clock Controller Card option switch settings
1
2
off
off
4
Connect the NT8D79AD cables from the primary and secondary
references to the faceplate of the clock controller card.
5
Route the NT1R04AA cable from the junctor board to the clock
controller card.
6
Connect the NT1R04AA cable first to the controller card, then to the
connector on the junctor panel.
Upgrade system installation Upgrading to Meridian 1 system options
SW1
3
4
1
off
off
off
Upgrades to Meridian 1 option 81
SW2
2
3
4
off
off
off
off
12-149
SW4
1
2
3
4
on
on
off

Advertisement