12. Check the LEDs on the PSMs. For each PSM, verify that the Input OK and Output OK LEDs are lit
steadily green, and that the FAULT LED is off.
NOTE: If the Input OK and Output OK LEDs do not light steadily or if the FAULT LED is lit,
see
"Troubleshooting the PTX5000 Power System" on page
13. On the external management device connected to the Routing Engine, monitor the startup process
to verify that the system has booted properly.
14. Repeat step 11 through step 14 for the other PDU.
NOTE: The Routing Engine boots as the PDU completes its startup sequence.
After powering on a power supply, you must wait at least 60 seconds before powering it off.

Verifying the Replaced SIBs

1. Bring the SIB online by using one of the following methods:
• Press and hold the ONLINE/OFFLINE button on the SIB faceplate. The green OK LED on the
faceplate begins to blink. Hold the button down until the LED blinks.
• Issue the following CLI command on the PTX5000:
user@host> request chassis sib online slot
2. To verify that all the new SIBs are installed, use the show chassis hardware command. The new SIBs ID
should be displayed in the command output (see
page
7).
To verify the status of the SIBs:
• Issue the show chassis fabric errors command at the [edit] hierarchy level to verify the link status
for each SIB.
Also use the show chassis fabric sibs command to check the link status for each SIB.
• Issue the show chassis fabric fpcs command at the [edit] hierarchy level to check whether any fabric
error is logged.
• Use the show chassis fabric topology to check the link status of all the SIBs and Packet Forwarding
Engines.
3. If there are any errors in the replaced SIB, debug the errors. See
Switch Interface Boards" on page
slot number
"PTX5000 Hardware Component Overview" on
616.
591.
"Troubleshooting the PTX5000
564