7.2.5.2 Replacing the Hydrogen Detection System

Prerequisites
Preparations
Do not operate with power on. Take appropriate insulation measures.
Tools: Phillips screwdriver, adjustable wrench, protective gloves
Materials: spare hydrogen detection system
Procedure
Step 1 Switch off the upstream circuit breaker of the hydrogen detection system to power off the
hydrogen detection system.
Step 2 Remove cables from the hydrogen detection system.
Step 3 Use a Phillips screwdriver to loose nuts on the mounting ears and remove the faulty hydrogen
detection system.
Step 4 Align the four mounting ears of the new hydrogen detection system with the expansion bolts,
and tighten the M6 nuts.
Issue 03 (2019-03-10)
When installing temperature sensors, bind the cables behind the sensors to the cable bridge,
keeping them 20 mm away from the sensor probes.
Temperature sensors must not be in touch with metal parts or cabinets.
Keep the temperature sensors facing the inside of the cabinets to ensure accurate
measurement of cabinet interior temperatures.
The hydrogen detection system needs to be replaced.
A spare hydrogen detection system of the same model is available and functional.