Connecting The Smart Cooling Product Monitoring Cable; Connecting The Netcol5000 Monitoring Cable - Huawei iManager NetEco 6000 Device Installation And Commissioning Manual

Hide thumbs Also See for iManager NetEco 6000:
Table of Contents

Advertisement

iManager NetEco 6000
Device Installation and Commissioning Guide
Figure 4-40 Connecting a monitoring cable to the door status sensor
Step 2 Prepare an RJ45 connector on one end of the network cable by following to the instruction in
4.3.1 Preparing a Monitoring
Step 3 Connect the green core wire 6 and the brown-white core wire 7 to the cables routed out from
the door status sensor.
Step 4 Connect one end of the RJ45 network cable to the AI/DI port on the ECC collector.
----End

4.3.6 Connecting the Smart Cooling Product Monitoring Cable

4.3.6.1 Connecting the NetCol5000 Monitoring Cable

Prerequisites
A network cable used for monitoring is prepared.
Context
When NetCol5000C-65kW&80kW, NetCol5000-A042/A035/A025/A020/C030 connect to
the NetEco over Modbus-RTU, connect cables by referring to this section.
Procedure
Step 1 Connect one end of the network cable to the communications port on the NetCol5000 side
panel.
Issue 03 (2019-03-10)
The COM port of NetCol5000C-65kW&80kW is on the main control panel at the smart
cooling product rear doors.
Copyright © Huawei Technologies Co., Ltd.
4 Connecting Monitoring Cables to Devices
Cable.