Figure 3-3 Installing a guide rail
1.
2.
3.
Step 2 Place the server on the guide rails and slide it along the guide rails into the cabinet.
Step 3 Align the two mounting ears of the server with the rack rail of the cabinet and tighten the
screws on the mounting ears.
Issue 03 (2019-03-10)
Place a guide rail horizontally on the installation position in the cabinet.
Fix the guide rail using rubber plugs.
a.
In front of the guide rails: If a server is installed using the upper mounting holes,
insert rubber plugs tightly into the holes at the middle. If a server is installed using
mounting holes at the middle, insert rubber plugs tightly into the upper holes.
b.
Behind the guide rails: Insert rubber plugs tightly into the upper mounting holes.
(Optional) To enhance the rigidness and seismic-proof performance of a server, you can
install bolts at the rear of flexible guide rails.