Creating An Ecc500 V6 Collector On The Neteco - Huawei iManager NetEco 6000 Device Installation And Commissioning Manual

Hide thumbs Also See for iManager NetEco 6000:
Table of Contents

Advertisement

iManager NetEco 6000
Device Installation and Commissioning Guide

6.4.1.5 Creating an ECC500 V6 Collector on the NetEco

Prerequisites
Procedure
Step 1 Choose Configuration > Configuration Management > Data Center Planning from the
main menu. The Data Center Planning page is displayed.
Step 2 Select the management domain to add a device. The management domain can be a rack,
power cabinet, or DDF.
Step 3 Click the management domain and choose Design under the
is displayed.
Step 4 In the lower-left corner of the page, click the Device tab.
Step 5 Click the drop-down list box in Type and select Collector.
Step 6 Select Collector and drag the icon to the inside of the cabinet.
Step 7 Specify parameters in the right pane based on the following table.
parameters.
Issue 03 (2019-03-10)
You have logged in to the NetEco client.
You have the operation rights for Data Center Planning.
You have created a management domain for the device to be added on the Data Center
Planning page.
To delete a device, click the device and choose Delete under
Copyright © Huawei Technologies Co., Ltd.
6 Adding Devices
. The page for adding a device
.
Figure 6-52
shows these