Figure 4-16 Main Control Panel
For NetCol5000-A035 and NetCol5000-A020, open the front door, and connect one end
of the network cable to the FE port on the side of the smart cooling product LCD.
Figure 4-17 FE ports on the NetCol5000-A035 and NetCol5000-A020
For NetCol5000-A042, NetCol8000-C070, and NetCol8000-C150, open the rear door,
and connect one end of the network cable to the FE_1 port on the main control module
of the smart cooling product.