Flow Overview
Figure 2-2 Flowchart for the installation and commissioning of NetEco devices
Recommended sequence of installing devices: devices inside the rack > devices outside the
rack > in-room devices.
Issue 03 (2019-03-10)
The collector is an ECC500 collector or ECC800 collector.
Ensure that the collector and the NetEco are installed in the same network segment.
The installation sequence can be adjusted based on the actual condition onsite.