System Hardware Manual
7.
Replace the battery connection cables to the battery box.

Figure 3-139 Replacing the CHSGW SMALL BATT BOX Fuse

Installing the External Batteries (CHS LARGE BATT BOX) to the
9.5" Gateway (CHS2U GW-US) or Base (CHS2U B-US) Chassis
An optional, CHS LARGE BATT BOX can be installed to provide external
battery power to the CHS2U GW-US chassis during a power failure. The
long-term battery box powers the system for approximately three hours.
Because of injury from falling equipment, wall mounting
the CHS LARGE BATT BOX is not recommended.
Mounting the CHS LARGE BATT BOX directly on the
floor is not recommended.
Due to possible water damage, floor mounting the 9.5"
chassis is not recommended by NEC.
The CHS BASE UNIT raises the height of the CHS
LARGE BATT BOX 120mm (4.72").
8.4.1
CHS LARGE BATT BOX Installation
To install the batteries in the CHS LARGE BATT BOX, refer to
Chapter
3, section
8.2.2 Battery Installation on page
Issue 2.0
3-94.